Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
A . The Sprint Backlog.
B . The Sprint Goal
C . The release plan.
D . Sprint Review minutes.

Answer: A

Latest PSM I Practice Questions with 197 Q&As

Updated Study Material | Instant Download | Detailed Answers and Explanations

Subscribe
Notify of
guest
2 Comments
Latifa
Latifa
2 years ago

B

madan
madan
5 years ago

correct is B . The Sprint Goal