Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
A . The Sprint Backlog.
B . The Sprint Goal
C . The release plan.
D . Sprint Review minutes.
Answer: A
Latest PSM I Practice Questions with 197 Q&As
Updated Study Material | Instant Download | Detailed Answers and Explanations
B
correct is B . The Sprint Goal