When is implementation of a Product Backlog item considered complete?

When is implementation of a Product Backlog item considered complete?
A . At the end of the Sprint.
B . When the item has no work remaining in order to be potentially released.
C . When QA reports that the item passes all acceptance criteria.
D . When all work in the Sprint Backlog related to the item is finished.

Answer: B