What would be three key concerns if the frequency were to be lowered to every two or three days?

The Daily Scrum is an event that happens every day.

What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

A The Scrum Master loses the ability to update the Gantt Chart properly.

B The Sprint Plan may become inaccurate.

C Too much work is spent updating the Scrum board before the meeting.

D The Product Owner cannot accurately report progress to the stakeholders.

E Impediments are raised and resolved more slowly.

F Opportunities to inspect and adapt the Sprint Backlog are lost.

Answer: BEF 

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments