Which of these may a Development Team deliver at the end of a Sprint?

Which of these may a Development Team deliver at the end of a Sprint?
A . Failing unit tests, to identify acceptance tests for the next Sprint.
B . An increment of software with minor known bugs in it.
C . An increment of working software that is “done”.
D . A single document, if that is what the Scrum Master asked for.

Answer: C