- All Exams Instant Download
How much of the Sprint Backlog must be defined during the Sprint Planning event?
How much of the Sprint Backlog must be defined during the Sprint Planning event?
A . Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.
B . The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
C . Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
D . Just enough to understand design and architectural implications.
Answer: B
Latest PSM I Dumps Valid Version with 197 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
C
The correct answer should be C, not B.
Hi team! I’ve notice that question n. 14 and question n. 76 are the same but with a different answer. Would you like to check which one is the right one?!? To me sounds correct C. enough so the… Thanks for your attention!