When is the Sprint Backlog created?

When is the Sprint Backlog created?
A . At the beginning of the project.
B . During the Sprint Planning meeting.
C . Prior to the Sprint Planning meeting.
D . During the Sprint.

Answer: B

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments