In which stage of strategic planning do managers develop action plans and assign staff members to projects?
In which stage of strategic planning do managers develop action plans and assign staff members to projects?
A . Evaluation
B . Development
C . Implementation
D . Formulation
Answer: C
Explanation:
During the strategy implementation phase of strategic planning, the plan is put into action. Managers develop action plans and allocate resources toward achieving organizational objectives.