If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?
A . Its productivity is likely to decrease.
B . Its productivity is likely to stay the same.
C . Its productivity is likely to increase.

Answer: A

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
2 Comments
Inline Feedbacks
View all comments
bonieta sievers
bonieta sievers
1 year ago

I also thought it was b, in another test the answer was it would stay the same because the excisting team would remain the same and only the new team would decrease.

Matthias
Matthias
2 years ago

In version 9.02 the answer was B.