When should a Sprint Goal be created?

When should a Sprint Goal be created?
A . It should have been created in the previous Sprint during Product Backlog refinement.
B . It must be established before Sprint Planning in order to begin planning.
C . A Sprint Goal is not mandatory in Scrum.
D . At any time during the Sprint.
E . During Sprint Planning.

Answer: E