A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
A . True
B . False
Answer: B
Latest PSM I Practice Questions with 197 Q&As
Updated Study Material | Instant Download | Detailed Answers and Explanations
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
this question once had True as an answer and once False )))) so what is the right one????
answer is False Not True because there are no release sprints in scrum. Also from what i am told that this question is not on the real exam but always good to know.
Hi Team!
I see that question n. 26 and n. 71 are the same but with opposite answer. Can you clear and let us know which one is the right one?
Thanks a lot for your time!