How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
A . The Scrum Team with the highest velocity pulls Product Backlog items first.
B . The Development Teams pull in work in agreement with the Product Owner.
C . The Product Owner should provide each team with its own Product Backlog.
D . Each Scrum Team takes an equal numbers of items.
E . The Product Owner decides.
Answer: B