When can a Development Team cancel a Sprint?

When can a Development Team cancel a Sprint?
A . It can’t. Only Product Owners can cancel Sprints.
B . When functional expectations are not well understood.
C . When the Product Owner is absent too often.
D . When the selected Product Backlog items for the Sprint become unachievable.
E . When a technical dependency cannot be resolved.

Answer: A