Which statement is correct about the Sprint Backlog?

Which statement is correct about the Sprint Backlog?
A . It doesn’t need to have detail.
B. It has just enough detail.
C. It has all the details.

Answer: B

Explanation:

The Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how).