Which 3 of the following are time boxed Scrum events?

Which 3 of the following are time boxed Scrum events?
A . Sprint Plannig
B. Sprint Refinement
C. Sprint Review
D. Daily Scrum

Answer: A,C,D

Explanation:

There is no Scrum Event named Sprint Refinement.