The Scrum Master can decide which Scrum Events are required in the Scrum project.

The Scrum Master can decide which Scrum Events are required in the Scrum project.
A . False
B. True

Answer: A

Explanation:

Scrum defines which Events are required in all Scrum project, not the Scrum Master. It is always required to have the Sprint Planning, the Daily Scrums, the Sprint Review and the Sprint Retrospective in every project.

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments