Which Scrum accountability (role = outdated term) is owning the Sprint Backlog?

Which Scrum accountability (role = outdated term) is owning the Sprint Backlog?
A . The Product Owner
B. The Scrum Master
C. The Development Team

Answer: C

Explanation:

To "own" something means, that you are accountable for it.