What should the team do?

The Product Owner is not available and cannot answer the developers questions before the Sprint Planning. Therefore, the developers feel a high level of uncertainty to make a reliable forecast .

What should the team do?
A . Extend the duration of the current Sprint and try to answer all questions.
B. The Sprint Planning meeting should be cancelled or postponed.
C. The upcoming Sprint should be cancelled.
D. The developers should make a best guess and should not worry too much.

Answer: D

Explanation:

Its always better to start a sprint. Nothing bad will happen if you are not able to deliver everything that you have selected under uncertainty!