What may happen if the Scrum Teams composition changes during the project?

What may happen if the Scrum Teams composition changes during the project?
A . The productivity will increase due to new ideas.
B. The roles are clearly defined – nothing will happen.
C. Often a short-term reduction in productivity can be seen.

Answer: C

Explanation:

It is okay to change the Scrum Teams composition, but often there will be a short-term reduction in productivity.