When is it allowed for a Scrum Master to cancel a Sprint?

When is it allowed for a Scrum Master to cancel a Sprint?
A . When the Sprint Goal is obsolete.
B. When the Developers ask the Scrum Master to do so.
C. The Scrum Master does not have the authority to do this.

Answer: C

Explanation:

It’s done by the Product Owner.

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments