Which statement about the Product Backlog is correct?

Which statement about the Product Backlog is correct?
A . The Product Backlog must only contain small, detailed and clearly described items.
B. The Scrum Master is responsible for managing the Product Backlog.
C. The Product Owner is responsible for managing the Product Backlog.

Answer: C

Explanation:

The Product Owner is responsible for managing the Product Backlog. It should be ordered by value and items at the bottom of the Product Backlog may be larger (not yet refined).