The Scrum Master can decide which Scrum Artifacts are required in the Scrum project.
The Scrum Master can decide which Scrum Artifacts are required in the Scrum project.
A . False
B. True
Answer: A
Explanation:
Scrum defines which Artifacts are required in all Scrum project, not the Scrum Master.