Which of the following are required by Scrum?

Which of the following are required by Scrum?
A . Hardening Sprints
B. Story Points
C. Time boxed events
D. Sprint Planning meetings
E. A Sprint 0

Answer: C,D

Explanation:

Hardening Sprints and a Sprint 0 are not allowed by Scrum. Story Points are recommended but not mandatory.