Which questions does the Sprint Planning answer?
Which questions does the Sprint Planning answer?
A . What can be delivered in the Increment resulting from the upcoming Sprint?
B. Who will do which Sprint Backlog item?
C . How will the work needed to deliver the Increment be achieved?
Answer: A,C
Explanation:
The Development Team is self-organized. That means that they will decide on their own who will do which tasks during the Sprint.