The Product Backlog is baselined before the Sprint 0.

The Product Backlog is baselined before the Sprint 0.
A . False
B. True

Answer: A

Explanation:

This statement is wrong because the Product Backlog is not baselined (fixed) and there is no Sprint 0 in Scrum.