Work Item Age metrics are most helpful in supporting which of the following? (choose the best two answers)

Work Item Age metrics are most helpful in supporting which of the following? (choose the best two answers)
A . Inspecting and adapting the Sprint at the Daily Scrum.
B. Inspecting and adapting the team’s process and definition of Workflow at the Sprint Retrospective.
C. Influencing the team’s Service Level Expectation (SLE).
D. Helping the team estimate the size of Work Items.
E. Being a leading indicator for the length of the feedback loop for a certain Work Item.

Answer: A,E

Explanation:

Work Item Age is a leading indicator for what a team’s cycle time (i.e. the length of the feedback loop) is likely to be for a certain item.

It is also a leading indicator to determine when an item, that is in progress, is likely to be ‘finished’ in

order for the team to adapt their Sprint.