True or False: The purpose of a Scrum Team’s Service Level Expectation (SLE) is to allow teams to give each Product Backlog item a commitment to a due date as part of Sprint Planning.

True or False: The purpose of a Scrum Team’s Service Level Expectation (SLE) is to allow teams to give each Product Backlog item a commitment to a due date as part of Sprint Planning.
A . True
B. False

Answer: B

Explanation:

The SLE is primarily an internal metric to help you inspect and adapt. However, the SLE CAN be used in Sprint Planning to provide the Product Owner and stakeholders with an idea of the service level that can be expected from the team. That does not include providing a specific date for each PBI in the SBL. The SLE enables the Scrum Team to forecast a finished date at a certain confidence level once the item has been started.