What does the Work Item Aging chart show? (Choose the best answer)
What does the Work Item Aging chart show? (Choose the best answer)
A . How many days has the team worked without breaching the WIP limits.
B. How many sprints ago has the team revised their WIP limits.
C. The approximate average age of work in process in the team.
D. For each item on the Kanban board how long ago has it been pulled into WIP.
Answer: D
Explanation:
WIP aging is one of the crucial flow metrics used in Professional Scrum with Kanban. Learn more in the Kanban Guide for Scrum Teams or this blog. It is especially useful during the Daily Scrum to help surface flow issues regarding specific PBIs.