The team needs to work on a high priority urgent unplanned item, but they are at their WIP limit.

The team needs to work on a high priority urgent unplanned item, but they are at their WIP limit.

True or False: They should change the WIP limit at their Daily Scrum to enable them to pull in that item.

B. True

C. False

Answer: C

Explanation:

If they do decide to pull in that item, it is a better approach to exceed the WIP limit as an exception and mark that exception than to adjust "the rules".