True or False: Scrum Events, Scrum Team Accountabilities, and Scrum Artifacts are changed when using Scrum with Kanban. For example, the Scrum Team might choose to omit the Sprint Retrospective when using Kanban with Scrum.

True or False: Scrum Events, Scrum Team Accountabilities, and Scrum Artifacts are changed when using Scrum with Kanban. For example, the Scrum Team might choose to omit the Sprint Retrospective when using Kanban with Scrum.
A . True
B. False

Answer: B

Explanation:

Adding Kanban to Scrum provides a technique to help the Scrum Team focus on driving a continuous flow of activity, but does not negate value provided by the Scrum Events, Artifacts, and Accountabilities.