True or False: Batch size is the same as the Sprint length when using Scrum with Kanban.
True or False: Batch size is the same as the Sprint length when using Scrum with Kanban.
A . True
B. False
Answer: B
Explanation:
Each activity in the Scrum Team’s Definition of Workflow can have its own batch size. For example, the team might deploy each Product Backlog item and then their deployment batch size would be 1, not the Sprint length.