As an Agile Leader, which of the following would be your top priority?

As an Agile Leader, which of the following would be your top priority?
A . Keeping the team members healthy.
B. Resolve internal team conflicts and disagreements.
C. Make sure team members are aligned with what the project is trying to achieve.
D. Controlling the team’s performance.
E. Comparing the performance of different teams based on their velocity.

Answer: C

Explanation:

By process of elimination, none of these are the responsibility of an Agile Leader, except making sure the team has a purpose and Project Goal.

Latest PAL-I Dumps Valid Version with 305 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments