Who is responsible for managing the progress of work during a Sprint?

Who is responsible for managing the progress of work during a Sprint?
A . The Scrum Master.
B . The Development Team.
C . The Product Owner.
D . The most junior member of the Team.

Answer: B

Explanation:

The correct answer is B, because the Development Team is responsible for managing the progress of work during a Sprint. The Scrum Guide states that “the Development Team tracks this total work remaining at least for every Daily Scrum to project the likelihood of achieving the Sprint Goal. By tracking the remaining work throughout the Sprint, the Development Team can manage its progress.”

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments