The Sprint Review is mainly an inspect and adapt opportunity for which group?

The Sprint Review is mainly an inspect and adapt opportunity for which group?
A . The Development Team and stakeholders.
B . The Product Owner and Development Team.
C . The Scrum Team and stakeholders.
D . The Product Owner and management.
E . The Development Team and management.
F . The Product Owner and stakeholders.

Answer: C

Explanation:

According to the Scrum Guide1, the Sprint Review is an informal meeting at the end of the Sprint, where the Scrum Team and stakeholders collaborate about what was done in the Sprint. Based on that and any changes to the Product Backlog during the Sprint, attendees collaborate on what to do next. The Product Owner explains what Product Backlog items have been “Done” and what has not been “Done”; the Development Team discusses what went well during the Sprint, what problems it ran into, and how those problems were solved; and the Development Team demonstrates the work that it has “Done” and answers questions about the Increment. The entire group collaborates on what to do next, so that the Sprint Review provides valuable input to subsequent Sprint Planning. The Sprint Review is mainly an inspect and adapt opportunity for the Scrum Team and stakeholders.

Reference: Scrum Guide