Which three of the following are feedback loops in Scrum? (Choose three.)
Which three of the following are feedback loops in Scrum? (Choose three.)
A . Sprint Review.
B . Release Planning.
C . Sprint Retrospective.
D . Refinement Meeting.
E . Daily Scrum.
Answer: A,C,E
Explanation:
The correct answers are A, C, and E, because these are feedback loops in Scrum. The Sprint Review is a feedback loop that allows the Scrum Team and the stakeholders to inspect the Increment and adapt the Product Backlog. The Sprint Retrospective is a feedback loop that allows the Scrum Team to inspect itself and create a plan for improvements. The Daily Scrum is a feedback loop that allows the Development Team to inspect its progress and plan its work for the next 24 hours.