When is it most appropriate for a Development Team to change the definition of “Done”?

When is it most appropriate for a Development Team to change the definition of “Done”?
A . During Spring Planning.
B . Prior to starting a new Sprint.
C . During the Sprint Retrospective.
D . Prior to starting a new project.

Answer: C

Explanation:

According to the Scrum Guide1, one aspect of Scrum Teams inspecting how they work toward their Product Goal is that they improve their definition of “Done” over time. The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. Therefore, it is most appropriate for a Development Team to change the definition of “Done” during the Sprint Retrospective.

Reference: Scrum Guide

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments