How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
A . The Scrum Team with the highest velocity pulls Product Backlog items first.
B . The Development Teams pull in work in agreement with the Product Owner.
C . The Product Owner should provide each team with its own Product Backlog.
D . Each Scrum Team takes an equal numbers of items.
E . The Product Owner decides.

Answer: B

Explanation:

The correct answer is B, because when multiple Scrum Teams work from the same Product Backlog, they should pull in work in agreement with the Product Owner. The Scrum Guide states that “multiple Scrum Teams often work together on the same product. One product goal unites them. Therefore, they must mutually define and comply with a definition of ‘Done’ that applies to their combined work product.” Therefore, they should collaborate and coordinate with each other and with the Product Owner to select Product Backlog items that align with their shared product goal.