Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
A . Run the Daily Scrum.
B . Prioritize the Development Team’s work on the Sprint Backlog.
C . Update the Sprint burndown chart.
D . Answer questions from the Development Team about items in the current Sprint.
E . Work with the stakeholders.

Answer: D,E

Explanation:

The correct answers are D and E, because these are two activities that a Product Owner can engage in during a Sprint. The Scrum Guide states that “the Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team.” Therefore, the Product Owner can answer questions from the Development Team about items in the current Sprint, and work with the stakeholders to understand their needs and expectations.

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments