You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar as the base calendar.Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks.When you assign a resource to one of these tasks, you get an error.You need to correctly assign the resource.What should you do?

You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar as the base calendar.Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks.When you assign a resource to one of these tasks, you get an error.You need to correctly assign the resource.What should you do?
A . Change the task type to Fixed Units, Effort Driven, and then re-assign the resource.
B . Select scheduling ignores resource calendars for the task.
C . Remove the night calendar from the task and re-assign the resource.
D . Change the task mode to Manually Scheduled.

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments