What should you do?

You are a program manager for a complex software development project.You use Project Professional 2013 to manage your project.Your resources work on many different projects across the program, and you need to resolve resource overallocations.Your project team uses a resource pool to manage resources.Resource1 has been assigned to assist on a project that is on the critical path.After assigning Resource2 to the task, you notice that Resource1 is overallocated during the month of November.Project A, which is on critical path, takes priority over Project B, which Resource1 is also assigned to.

Using resource leveling in Project Professional 2013, you need to resolve the overallocation for Resource1 for the month of November only.

What should you do?
A . Set the priority of Project A to 1000 and the priority of Project B to 500.Change the leveling order to Standard, and select Level All.
B . Set the priority of Project A to 1000 and the priority of Project B to 500.Set the Leveling Range for November.Change the leveling order to Priority, Standard.Select Level Resource, and choose Resource1 and Level Now.
C . Set the priority of Project A to 500 and the priority of Project B to 1000.Set the Leveling Range for November.Change the leveling order to Standard and select Level Resource.Then choose Resource1 and Level Now.
D . Set the priority of Project A to 500 and the priority of Project B to 1000.Change the leveling order to Priority, Standard, and select Level All.

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments