What should you do?

You are a project manager who uses Project Professional 2013.You are creating a project with several phases.Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks.The delivery phase includes a summary task, which consists of five separate sub tasks.You need to monitor this phase closely to ensure that it does not overrun.

What should you do?
A . Set a deadline date for the automatically scheduled summary task for four weeks after July 1.Monitor the progress of the summary task against the deadline.
B . Create an automatically scheduled summary task of 20 days.Set the start date to July 1.
C . Create a manually scheduled summary task of 20 days.Create a deadline for the task which is set to July 29.Monitor the progress of the summary task against the deadline.
D . Create an automatically scheduled summary task of 20 days.Set the finish date to July 29.
E . Create a manually scheduled summary task of 20 days.Enter a Finish No Later Than constraint which is set to July 29.

Answer: A