You are a project manager, and your organization uses Project Professional 2013.You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.What should you do?

You are a project manager, and your organization uses Project Professional 2013.You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.What should you do?
A . Right-click the resource and reassign it to the underallocated resource.
B . Drag the underallocated resource on the task to reassign it.
C . Right-click the task and reassign it to the underallocated resource.
D . Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.

Answer: C