You are a project manager who uses Project Professional 2013.You are planning an office move, which will occur over a weekend.You use Auto Scheduled tasks and create a weekend working calendar.You need to assign the weekend working calendar to the task.What should you do?

You are a project manager who uses Project Professional 2013.You are planning an office move, which will occur over a weekend.You use Auto Scheduled tasks and create a weekend working calendar.You need to assign the weekend working calendar to the task.What should you do?
A . Click on the Task tab and select the Change Working Time button.Assign the weekend working calendar to the task.
B . Assign the task calendar to the task using the Task Information dialog box.
C . Right-click on the weekend on the Gantt chart and select the weekend working calendar.
D . Change the start date of the task to the Saturday, which will assign the weekend working calendar to the task.

Answer: B