You are a project manager who uses Project Professional 2013.You work on a construction project that requires propane as a fuel source for your equipment.The foreman requires that you enter project costs associated with all work completed on your project.The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane.Each time the tank is refilled, you must pay a fee of $20.You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time.

What should you do?
A . Create a cost resource, add the resource to a task, and enter $25 in the actual cost.
B . Create a material resource with a material label of gallons.Enter $20 in the cost per use and $5.00 in the standard rate.
C . Create a cost resource, add the resource to a task, and enter $2520 in the actual cost.
D . Create a material resource with a material label of gallons.Enter $20 in the standard rate and $5.00 in the cost per use.

Answer: B