Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?

Which type of scheduling chart utilizes predecessor and successor relationships when identifying tasks?
A . PERT
B . Calendar
C . Milestone
D . Gantt

Answer: A

Latest RCDDv14 Dumps Valid Version with 288 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments