When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)

When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)
A . If This Then That (IFTT)
B . Gantt Chart
C . Work Breakdown Structure (WBS)
D . Critical Path Method (CPM)
E . Program Evaluation Review Technique (PERT)

Answer: B, D