What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?

What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?
A . After the contract is awarded and before project close out
B . As part of the contract bid process to prevent project delays
C . Before the contract is awarded
D . At the beginning of the close out process

Answer: A