In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?

In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?
A . CD
B . SD
C . PD
D . DD

Answer: B

Latest RCDDv14 Dumps Valid Version with 288 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments