Which of the following would be appropriate as a measure of test coverage?

The business has asked for a weekly progress report .

Which of the following would be appropriate as a measure of test coverage? 2 credits
A . Percentage of business requirements exercised
B . Percentage of planned hours worked this week
C . Percentage of countries that have test scenarios
D . Percentage of test iterations completed

Answer: A