The introduction of reviews and inspections has often failed as a process improvement action. Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail. 2 Credits (for 2 out of 3 correct 1 credit)

The introduction of reviews and inspections has often failed as a process improvement action. Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail. 2 Credits (for 2 out of 3 correct 1 credit)
A . Process ownership and experienced moderators who drive the inspection process.
B . Management support
C . Training of those involved
D . The availability of stands and processes
E . Usage of a more traditional software development lifecycle
F . Alignment with software process improvement
G . Using a reference model, e.g. TMMi

Answer: A,B,C

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments