Which is NOT a valid reason for using entry and exit criteria?

Topic 15, Scenario 9 "Test Management Documentation"

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing.

As part of the test strategy, entry and exit criteria will be defined for each test level .

Which is NOT a valid reason for using entry and exit criteria? 1 credit
A . The expectation is that development testing is not adequate.
B . Exit criteria are used to decide on when to stop testing.
C . Entry and exit criteria are a principal way for getting adequate resources.
D . Using entry and exit criteria will prevent software that is not or poorly tested from going to the next test level.

Answer: C